09/20/13 - Structural Team attained ASSHTO
-
09/21/13 - Geotechnical Team attained boring logs and site plans from Industry advisor.
-
10/03/13 - Structural Team began calculations for an estimation of number of girders.
-
10/04/13 - Geotechnical Team created soil profile and began calculation of soil properties.
-
10/06/13 - Structural Team determined that 6 girders would be the optimal quantity of girders.
-
10/15/13 - Structural Team began an intial design for the cross-section properties of the I-beam girder.
-
10/20/13 - Sturctural Team began calculations for all active loads.
-
10/28/13 - Geotechnical Team calculated soil properties.
-
10/30/13 - Preliminary Design Presentaion.
-
11/10/13 - Structural Team determined the loads, according to AASHTO specifications
-
11/26/13 - Rough Draft of Technical Paper
-
11/26/13 - Geotechnical Team determined the axial capacity
-
11/26/13 - Geotechnical Team determined the driveability of piles.
-
02/02/14 - Structural Team designed I-beam for Flexure
-
03/13/14 - Structural Team checked the I-beam for Shear.
-
03/15/14 - Geotechnical Team driveability analysis was completed.
-
04/07/14 - Structural Team designed the bearing plates.
-
04/16/14 - Structural Team final I-beam section was developed
-
04/17/14 - Structural Team determined the spacing of stiffeners.
-
04/23/14 - Rough Draft of Technical Paper was submitted.
-
04/30/14 - Final Presentation